Nowadays, the utility has begun to consider the non-conventional electrical power is pollution free and economic. The non-conventional energy source mobile telecom station is more beneficial as compare diesel operated station. In this paper six different hybrid combinations are investigated on the base of economic, renewable factor, emission for electrified mobile telecom station, HOMER software is used to design hybrid combinations. The output result of HOMER show PV/Wind/Battery/DG system is feasible configuration amongst all six combinations. The PV/Wind/Battery/DG hybrid system has lowest cost of energy (0.50$), total net present cost ($100,666) and renewable factor (100%).
Keywords: Wind turbine; Solar photovoltaic cell; HOMER; Hybrid system
In present day’s need of electricity is increase all over the world. The conventional resources of energy are diminishing in future years. The conventional fuel also produces emission which affects environment and human health. To resolve all thus issue renewable energy source is based alternative. Renewable energy source is available abundantly in environment without any cost. India has great potential of renewable energy resource and demand of electricity is increase day by day because of developing economic [1]. The telecom industry of the India is grooving very fast. Presently all the telecom base power station (TBPS) running on diesel generator. The operation of TBPS is very costly due diesel fuel price so that an alternate solution is suggested in paper as renewable energy for source TBPS. The various hybrid combinations for rural location are demonstrated to find the optimal solution regarding cost of energy, reliability, total net present cost and renewable factor. The design location for TBPS has Latitude 19_6350N and Longitude 81_672E which is in Bastar, Chhattisgarh, India.
Figure 1:Grid connected and diesel generator telecom base station.
The TBPS is considered as an essential load. The BTS could be a telecommunication base accustomed encourages remote correspondence between supporter appliance and telecoms administrator system. The worldwide advancement of BTS is increasingly occurring in areas in which the ability conveyance framework often separates for drawn out stretches of time or where there’s no entrance to the ability provide the system. That the TPBS in such space, DG with battery unit’s area unit used to maneuver down the network for power provide and guarantee system accessibility. Nonetheless, these oblige associate abnormal state of support work and devour moderately high measures of diesel oil for low-level yields. Consequently, DG acquire higher working price. The cost of energy is increase because of change in cost of fuel and issues over obtaining emission have created the telecom organizations to focus on improved power administration routines. This power provides the theme for grid connected and the diesel generator telecom base station is pictured in Figure 1 this technique delivers very high expense due to heavy reliance on diesel generator and worse performance of batteries [2]. Within this recommended method telecom base section regarded as fill considered since 49.77kWh/d as well as peak fill regarding day, time is 4.42kW. The info had been tested to the get worse per hour assumption every day fill requirement of an old-fashioned TBSP. The information was calculated to aggregate hourly premise everyday energy demand prerequisite for rustic telecom. Daily, seasonal and yearly profiles of load data are shown in Figure 2.
Figure 2:Daily, quarterly and yearly profile of load data.
Figure 3:Global horizontal radiation and clearness index.
The PV resource data used for planned hybrid installation at a site of 19_590N latitude and 81_590E of longitude information from NASA Meteorology. The annual average solar irradiation and also the average clearness index were found to be 4.99kWh/m2/Day and 0.530 severally. The actual photovoltaic radiation is available whole year round; therefore, an outsized deal of photovoltaic energy productivity is obtained it’s pictured in Figure 3. The utmost solar power obtains in summer season [3]. A 5kW solar photovoltaic array is linked in series parallel while using the recommended hybrid system. At the position, if the sun rays strike SPV panels, it provides electrical power. Regarding recommended hybrid system, set up charge in addition to replacing charge is usually $5000 in addition to $3000 from the 1kW solar panel. The SPV attached to DC hyperlink and also the de-rating factor from of the array is 80%. Slope, the ground reflectance in percentage and azimuth (Degrees West to East) are 19.9833, 20 and 0 respectively. The weather data of proposed hybrid system location shown in Table 1.
Table 1:Monthly solar data.
The Wind energy resource data is shown in Figure 4 the average wind speed data throughout the year [4-10]. BWC Excel-R (XLR) turbine is used in the suggested hybrid renewable system. Avail of power as of the wind turbine relies incredibly on wind variation. In this manner, the wind rotary engine rating is by and massive a lot of higher contrasted with the traditional electricity demand. During investigation, Wind Power’s XLR design is thought of. The lifespan of a wind turbine is to be twenty years. The rated capacity of this turbine 7.5kW DC. The installation cost, replacement and maintenance price of this rotary engine are $1500, $1200 and $75 respectively. The wind turbine power curve and wind variation with height are shown in Figure 5a & 5b.
Figure 4:Average monthly wind speed curve.
Figure 5a:Wind turbine power curve.
Figure 5b:Wind variation with height.
The size of the generator is 1kW recognized as for a hybrid system. The principal cost, replacement cost and O&M cost of the generator is usually $325, $225 along with $0.520 respectively. Fuel used for the generator is usually a diesel engine along with the money necessary for diesel-engine usually varies according to overseas current market situation. The variation in diesel price is used for sensitivity examination as well as dissimilar values of diesel fuel cost are 0.8$/L, 0.85$/L, and 0.89 $/L is introduced. The life of generator is usually consumed since 15,000 operating hours. HOMER guarantees this aggregate functioning pace of the generator in view of the measure of the time this should be used as part of 12 months. The minimum load ratio is 30%. Intercept Coefficient is 0.08 L/hr/kW rated and the slope (marginal fuel consumption of the generator) is 0.25L/hr/kW/output. The generator is plugged in to the AC side of the HOMER design model and size for the feasible optimal system are 1kW,2kW,5kW and 10kW considered. The relation between efficiency and output of the generator and fuel curve are shown in Figure 6a & 6b.
Figure 6a:Generator efficiency curve.
Figure 6b:Fuel curve.
The proposed technique is off-grid one in order that some sort of battery power standard bank can be used for just a backup technique along with which in turn additionally keeps regular voltage across the load. The vision 6FM200D battery power can be used to optimum hybrid system [11-15]. The item is comprised 12V, 198Ah, along with 2.4kWh; suggested lifespan throughput is 917kWh along with connected in series/parallel setting. Principal cost, replacement cost and O&M cost is $280, 195$ and $5 correspondingly. Battery bank state of charge shown in Figure 7.
Figure 7:Battery bank state of charge.
The particular SPV array output DC at a voltage, which depends on the specific settings along with the sunshine-oriented radiation. The DC control then races to an inverter, which changes over it into standard alternating current (AC) voltage. Inverters often operated as a part of extensive scale applications are main inverters that propose easy establishment and high performance. The sizing of the particular inverter is demand in entering direct current (DC) energy in the SPV and also productivity energy of alternating electric current connected to the particular grid. The proper sizing of inverter possesses skillful to take the most energy from the SPV as well as lower the price of the particular inverter without worrisome the particular operations in the system. The lifespan of the converter is 20 year and efficiency are 90%. Principal cost, replacement cost and O&M cost of the converter is .620, 330 and 0.0 respectively [16].
This section deals with the result of our analysis. The optimization results are presented for different type of six operating modes, which is tracked by results of the sensitivity scrutiny. The proposed system is considered at 5.00 kWh/m2/day global solar radiation and 3.5m/sec wind speed [17]. The environmental aspect of system configuration is also considered by performing emission analysis. For obtain optimal solution, five different types of PVWind hybrid combinations such as SPV/Batt/DG, WT/Batt/DG, SPV/WT/DG, SPV/WT/Batt and SPV/WT/Batt/DG are analysis. All five-hybrid combination model is shown in Figure 8.
Figure 8:All six combination of hybrid system.
HOMER performs simulations with respect to a number of inputs given. It identifies the best hybrid system configuration based on several combinations of equipment and their cost and ranks them in ascending order on the basis of least NPC in Figure 9a. A list has been presented for different configurations. Six hybrid configurations have been selected for SPV/Batt/DG connected load. The first configuration which is the most cost effective one gives the lowest COE of $0.595kWh and lowest NPC of $119,304 through a renewable factor of 81% is designed with a 10kW SPV, 1 kW DG, 30 battery and 6 kW converters. The operating and initial cost is $4,448 and $62,445 respectively. Figure 9b show the monthly average electrical energy output in support of most economic hybrid configuration i.e. the first one. Figure 9c shows the cash flow summary for various equipment’s of the most economic hybrid configuration [18]
Figure 9a:A list has been presented for different configurations.
Figure 9b:Shows the monthly average electricity output.
Figure 9c:Shows the cash flow summary for various equipment’s of the most economic hybrid configuration
HOMER performs simulations with respect to a number of inputs given. It identifies the best hybrid system configuration based on several combinations of equipment and their cost and ranks them in ascending order on the basis of least NPC. In Figure 10a a list has been presented for different configurations. Six hybrid configurations have been selected for WT/Batt/DG connected load. The first configuration which is the most cost effective one gives the lowest COE of $0.679kWh and lowest NPC of $132,693 with the renewable fraction of 100% is configured with a 5kW wind, zero diesel generator, 30 battery and 6 kW converters. The operating and initial cost is $3,365 and $89,620 respectively. Figure 10b shows the monthly average electricity output. Figure 10c shows the cash flow summary for various equipment’s of the most economic hybrid configuration.
Figure 10a:List has been presented for different configurations
Figure 10b:Shows the monthly average electricity output.
Figure 10c:Shows the cash flow summary for various equipment’s
HOMER performs simulations with respect to number of inputs given. It identifies the best hybrid system configuration based on several combinations of equipment and their cost and ranks them in ascending order on basis of least NPC. Figure 11a a list has been presented for different configurations. Six hybrid configurations have been selected for SPV/WT/DG connected load. The first configuration which is the most cost effective one, gives the lowest COE of $1.47kWh and lowest NPC of $301,870 with renewable fraction of 81% is configured with a 10kW PV, 10kW wind, 1kW diesel generator, and 6 kW converters. The operating and initial cost is $3,365 and $209,045 respectively. Figure 11b show the monthly average electricity output for most economic hybrid configuration i.e. the first one. Figure 11c show the cash flow summary for different apparatus of the most economic hybrid configuration. This SPV/WT/DG hybrid system is not feasible solution regarding the stability issue. Renewable penetration has high enough to potential cause stability problem because no storage device in the system.
Figure 11a:List has been presented for different configurations.
Figure 11b:The monthly average electricity output.
Figure 11c:Shows the cash flow summary for various equipment’s of the most economic hybrid configuration
HOMER performs simulations with respect to number of inputs given. It identifies the best hybrid system configuration based on several combinations of equipment and their cost and ranks them in ascending order on basis of least NPC. In Figure 12a a list has been presented for different configurations. Six hybrid configurations have been selected for SPV/WT /Batt connected load. The first configuration which is the most cost effective one, gives the lowest COE of $0.501kWh and lowest NPC of $100,666 with renewable fraction of 100% is configured with a 5kW PV, 2kW wind, 40 battery units and 6 kW converters. The operating and initial cost is $2,327 and $70,920 respectively. Figure 12b shows the monthly average electrical energy production for most economic hybrid configuration i.e. the first one. Figure 12c shows the cash flow summary for various equipment’s of the most economic hybrid configuration.
Figure 12a:List has been presented for different configurations.
Figure 12b:The monthly average electricity production for most economic hybrid configuration.
Figure 12c:Shows the cash flow summary for various equipment’s of the most economic hybrid configuration.
HOMER performs simulations with respect to number of inputs given. It identifies the best hybrid system configuration based on several combinations of equipment and their cost and ranks them in ascending order on basis of least NPC. Figure 13a a list has been presented for different configurations. Six hybrid configurations have been selected for SPV/WT/Batt/DG connected load. The first configuration which is the most cost effective one, gives the lowest COE of $0.544kWh and lowest NPC of $110,770 with renewable fraction of 81% is configured with a 5kW PV, 1kW wind, 0kW diesel generator, 40 battery units and 6 kW converters. The operating and initial cost is $4,307 and $55,745 respectively. Figure 13b shows the monthly average electricity output for most economic hybrid configuration i.e. the first one. Figure 13c shows the cash flow summary for various equipment’s of the most economic hybrid configuration [19].
Figure 13a:A list has been presented for different configurations.
Figure 13b:Shows the monthly average electricity output.
Figure 13c:Shows the cash flow summary for various equipment’s.
The design of all combination through the HOMER software tool, which provide simulation results on base of lowest total net present cost, lowest cost of energy, and renewable factor. All sixcombination analysis describe in this section.
a. Emission: Amongst all six combinations only system which not produce any harmful emission such SPV/WT/Batt, SPV/WT/Batt/DG have not produced any gases.
b. Production: According to the simulation analysis, we found that the capability shortage among all told cases is lower in SPV/WT/Batt/DG (3,161.7) and SPV/WT/Batt system in both combinations. It suggested that can be designing to fulfil required load demand.
c. Cost ($): The simulation result, it is analyzed that the system connected with SPV/WT/Batt/DG has lowest total net present cost $100,666, levelized cost $0.5012 and operating cost $2327 as compared to hybrid combinations.
d. Fuel: The DG connected system increase the cost of hybrid system. Above discussed results it is clear that the SPV/WT/ Batt/DG hybrid system has no fuel consumption. So, the SPV/ WT/Batt/DG system is feasible solution.
Fonts, Because of the relentless development of telecom market and related ventures in India, there’s a need to build up another Power supplies. It’s actual that the offer of telecom development in provincial territories is a long way from metro cities. In this paper various combination of SPV, Wind and DG and Battery hybrid system are investigated for obtaining feasible solution. This investigation found SPV/WT/Batt or SPV/WT/Batt/DG are often feasible as this kind of has no CO2 and CO emissions. Both the combination has lower cost of energy, total net present cost and environment friendly. SPV/WT/Batt/DG hybrid renewable energy system provide more promising results regarding cost of energy, total net present cost and renewable factor, emission and electrical production amongst all six combination. The simulation results in this paper can play a useful role in the application of hybrid renewable energy system for rural TBPS projects. The obtained results can be modified by reducing the cost of components if central and states government provide subsidy.