Local Raw Material, Fuel and Clinker Production Processing with 5 Stage Pre- Calciner Kiln and Grate Cooler in Georgia

  • Open or CloseChkheidze V*

    Georgian Technical University, Georgia

    *Corresponding author: Chkheidze V, Georgian Technical University, Georgia

Submission: December 26, 2020 Published: January 25, 2021

DOI: 10.31031/PPS.2021.04.000577

ISSN 2637-8035
Volume4 Issue1

Abstract

In Kaspi cement plant (Heidelbergcement group) the new 5 stage pre-calciner kiln (3000 TPD) was erected in 2016 and commissioned in 2018. It was a brownfield project, the existing wet plant was stopped with 3 long wet kilns, only cement grinding mills remain in operation. It is quite common thing to upgrade old process equipment with new installations but in this case source of main material, limestone was also changed, it was quite challenging.
My PHD work is related to the new production process and control concepts which were necessary to implement for keeping high production, low power and heat consumption and most importantly excellent quality to build the future.

Keywords: Clinker; Kiln; Pre-calciner; Raw materials; Production; Clinkerization; Quality; Incorporation